Commission recommends approval of inland‑port rezone amid traffic and UDOT scheduling questions
Summary
The commission recommended a favorable approval to the county council for rezone REZ2025‑093 (Inland Port parcels). Commissioners and staff flagged UDOT’s role, a traffic study projecting up to 13,000 trips at build‑out and concerns about truck routing through Grantsville and Hailey Road.
Get email alerts on the Rezone Inland Port topic
No spam. Unsubscribe anytime.
The Tooele County Planning and Zoning Commission voted unanimously to recommend that the county council approve rezone application REZ2025‑093, which would change the zoning on several parcels within the inland‑port area.
Planning staff explained the rezone covers multiple parcels and that a separate platting step will define precise buildable areas and floodplain constraints. Staff said the parcel legal descriptions will be provided before any council action and clarified this agenda item is a rezone recommendation rather than a final plat.
Commissioners focused on transportation impacts. The traffic study referenced in the applicant’s materials reported a maximum projection of roughly 13,000 daily trips in the study area by long‑term buildout. Staff and commissioners noted that the applicants’ schedule for business tenants is not fully formed, so the study used a high‑end projection. Trish told the commission that UDOT had received the traffic study and was considering it for the agency’s 2040 plan; commissioners had previously tabled a similar application to await UDOT input.
Several commissioners raised questions about truck routing and whether heavy trucks could be limited from using local roads through Grantsville or Hailey Road. Planning staff said current access limitations and where infrastructure is provided determine truck access; they noted some early construction used Higley Road because other access was incomplete, but once site access is constructed the applicant would not be able to use Higley for truck access.
There were no public comments. After discussion Commissioner Dow moved and Commissioner Scott seconded a motion recommending approval of REZ2025‑093 to the county council; the commission recorded a unanimous roll‑call vote in favor.
The commission attached the administrative expectation that UDOT receive and consider the traffic study; further permitting, platting and any UDOT mitigation would be addressed in later reviews.