Board approves $35,000 increase to Sequoia Eighth Grade Academy design contract for additional services

5576117 · August 12, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board approved Amendment No. 1 to the Narrate Designs contract for the Sequoia Eighth Grade Academy, adding $35,000 to the contract for additional design work including an ICC storm-shelter peer review, engineered retaining-wall plans required by the city, and administrative-area changes.

The Broken Arrow Public Schools Board approved Amendment No. 1 to the Narrate Designs contract for the Sequoia Eighth Grade Academy project, resulting in a net increase of $35,000 to the contract dated May 9, 2022.

"There were three specific additional services that resulted in this increase," said Mr. Leach, the district presenter. He listed a peer review for storm-shelter design required by the International Code Council (ICC), engineered plans for a large retaining wall required by the City of Broken Arrow, and additional work to reconfigure the administrative area after a decision changed how the building would be administered as construction began.

The board was told the increase covers additional professional design work; staff said the increase will be paid from bond funds. The motion to approve the amendment passed on a unanimous roll-call vote: Dr. Williams, Mrs. Taylor, Dr. Brandy Roulette, Mr. John Cockrell and Mr. Allen voted yes.

Discussion vs. decision: the presentation described specific, code-driven and site-driven design changes (storm-shelter peer review, engineered retaining wall plans, and administrative-area revisions). The board approved the contract increase; staff did not provide a detailed line-by-line cost breakdown beyond the $35,000 net increase during the public discussion.

Background: project documents presented at the meeting reference compliance with ICC guidance for storm shelter design and typical municipal requirements for engineered retaining walls.