Board sets Aug. 19 hearing on capital improvement plan bonds and approves two right‑of‑way acquisition resolutions
Summary
On Aug. 5 the Blue Earth County Board scheduled an Aug. 19 public hearing to consider adoption of the county’s Capital Improvement Plan and issuance of CIP bonds and approved resolutions authorizing right‑of‑way acquisition for two highway reconstruction projects (CSAH 5 and CSAH 69).
Get email alerts on the Capital Bonds Right Of Way topic
No spam. Unsubscribe anytime.
The Blue Earth County Board set a public hearing for 9 a.m. on Tuesday, Aug. 19 to consider adoption of the county’s Capital Improvement Plan (CIP) and authorization to issue capital improvement plan bonds, and it approved two separate resolutions authorizing right‑of‑way acquisition for upcoming road reconstruction projects.
Candace Sonic, the county finance director, asked the board to schedule the public hearing and to authorize publishing the required notice “in accordance with Minnesota statute section 373.4,” saying the county intends to issue CIP bonds to finance construction of a public works facility outlined in the CIP. The board approved the Aug. 19 hearing and authorized staff to publish statutory notice.
The board also approved right‑of‑way acquisition resolutions for County State Aid Highway (CSAH) 5 (reconstruction scheduled for 2026, Riverfront Drive to Cleveland Avenue) and for CSAH 69 (CSAH 69 between west and east intersections with U.S. Highway 169 in South Bend Township). Each resolution passed by unanimous voice vote.
In the public works report, staff described multiple ongoing highway and bridge projects, including bridge replacements, paving and signal work on CSAH 82 (Victory Drive), Culvert and box culvert replacements, grading and reclamation on several county roads, and progress toward submitting plans to MnDOT state aid for the CSAH 5 reconstruction. Staff said the CSAH 82 project remains on track for an Aug. 22 completion date.
Why this matters: the CIP hearing starts the formal public process required before the county may adopt the CIP and issue bonds; the right‑of‑way authorizations allow staff to acquire land interests needed to build scheduled reconstruction projects.
Next steps: the board will hold the Aug. 19 public hearing on the CIP, and staff will proceed with right‑of‑way acquisition activities and continue design and permitting for the listed roadway projects.