Board hears detailed timeline for CTE renovation, locker‑room addition and bond program at Ossining High School
Summary
Ossining, N.Y. — District staff and the lead architect on July 30 presented a phased schedule for the high‑school bond program that centers on a new Career and Technical Education (CTE) building, a two‑story addition above renovated locker rooms and a renovation of the former church building into CTE space.
Ossining, N.Y. — District staff and the lead architect on July 30 presented a phased schedule for the high‑school bond program that centers on a new Career and Technical Education (CTE) building, a two‑story addition above renovated locker rooms and a renovation of the former church building into CTE space. The presentation matters because the projects will move most high‑school programs into new or renovated spaces over several years and depend on state and federal approvals before contractors can begin demolition and site work. Lead architect Dave told the board, “The first 4 projects you see here are the capital projects that are underway or in process.” Project leaders described Phase 0A and 0B as preparatory demolition: 0A for the rectory and 0B for an annex adjacent to the church. As Mary Fox Filter summarized the regulatory status, Phase 0A “is awaiting final approval of the State Historic Preservation Office and the…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat