Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the County Infrastructure Updates topic
No spam. Unsubscribe anytime.
County engineer updates committee on roads, bridges: Golden Bridge guardrail delay, Kruger Bridge latex overlay nearing completion
Summary
County staff reported progress and timelines for bridge and road projects: Golden Bridge guardrail delivery expected this week, PJ Keller near completion, Stringtown waiting on contractor punch list, Kruger Bridge received a latex overlay pour and will require curing before reopening, and Tawanda–Gridley milling started.
Get email alerts on the County Infrastructure Updates topic
No spam. Unsubscribe anytime.
County highways staff provided project‑by‑project updates to the Land Use and Transportation Committee on Aug. 5. Golden Bridge (Lexington–Leroy Road): staff said guardrail is expected to arrive Thursday and crews will groove and seal the deck; the contractor must finish by the Aug. 15 deadline. PJ Keller Highway: the project is nearly complete, with guardrail and reflectors installed; rumble strips on safety shoulders remain to be placed by a subcontractor. Stringtown Road: mainline paving and striping are complete; the contractor still needs to finish incidental driveway and side‑road work and is expected back before the end of the week. Kruger Bridge (west of Hudson): crews used a hydro‑scarifier to remove about the top inch and a half of concrete to address delaminations, repaired loose rebar, and poured a latex overlay mixed on‑site. Staff described a curing regimen (dry cure two days, wet cure two days) and said contractors will groove and profile approaches before reopening. "We put, like, 3 inches of overlay on it…next week or two this will be open back up as well," staff said. Tawanda–Gridley Road: contractor began milling the existing surface and will follow with overlay work; the same contractor that completed PJ Keller is performing the work. No votes were taken on these status reports; staff asked the committee to note timelines and remaining punch‑list items.

