Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Transportation topic

No spam. Unsubscribe anytime.

County engineer flags road-widening, bridge and sidewalk actions tied to Jasper wastewater and INDOT projects

5532948 · August 4, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

DuBois County engineer updated commissioners on Portersville Road widening tied to a city of Jasper wastewater project, a potential permanent closure of County Road 250 at Route 56, a planned Lady Bridge rehabilitation estimated at about $700,000, and the community crossings grant status.

DuBois County's engineer briefed commissioners Aug. 4 on several transportation projects that could affect local traffic and budgets, including discussions with the city of Jasper about widening Portersville Road to support a proposed wastewater treatment plant and a possible permanent closure of a short segment of County Road 250 in Ireland as part of an INDOT sidewalk project.

Portersville Road and Jasper wastewater: The city of Jasper has proposed a wastewater treatment plant near the intersection of Portersville Road and 500 North and has asked whether the county has concerns about a small widening (the engineer said the request is for roughly a foot on one side and two feet on the other across an about 50-foot-long section). The engineer said the city would accept responsibility for associated costs and that any county approvals or right-of-way work would be brought to the board for formal action if needed.

County Road 250 closure discussion: INDOT and the project designer (HWC Engineering) have discussed incorporating a short (about 100'200 feet, per staff estimate) section of County Road 250 into a sidewalk project on State Road 56; the county engineer said the segment's skewed intersection with State Road 56 and the lack of a turn lane create safety concerns for large trucks and school traffic. The engineer said he would evaluate traffic and semi-turning maneuvers, consider possible intersection widening at the adjacent intersection, and seek public input before making a formal recommendation.

Bridges and grants: The engineer said plans for Lady Bridge No. 78 (Division Road over the Potomac River) are in development with consultant American StructurePoint; a preliminary construction estimate is in the $700,000 range. He described the work as a deck rehabilitation that preserves existing piers and foundations and would be let later this year for construction next year. The Community Crossings matching grant program was also discussed; staff noted the program's maximum had been lowered from $1.5 million to $1.0 million for a second round and said the county would examine eligibility for additional grant funding.

Other items: The engineer reported that Calabar is paving Old Road 45 and 600 North this week and will return to finish projects in September'October; he also reported progress on Club Road and smaller bridge/box-culvert projects and said a meeting with Cross Mine solar project managers is scheduled for Aug. 19 to coordinate road-use expectations and agreements.

Ending: The engineer said he would return to the board with specific recommendations if the county needs to cooperate on right-of-way or closure items and that public outreach would precede any permanent closures.