District construction update: CMU firewalls topped out, slabs poured and metal buildings delivered
Summary
Project manager Brian Cohen told the board that concrete masonry unit firewalls at the Beverly Hills replacement site are topped out, classroom C slab was poured, metal pre‑engineered buildings were delivered at multiple sites and curb-and-gutter work and utility taps are underway across projects.
Get email alerts on the School Construction topic
No spam. Unsubscribe anytime.
Cabarrus County Schools staff provided the board with construction progress reports on multiple projects, including the Beverly Hills replacement, Mary Frances Wall, Opportunity School and the transportation fuel farm. Brian Cohen, presenting the update, said at the Beverly Hills site "our concrete masonry units ... continue going vertical in the kitchen and serving line areas" and that the two large classroom CMU firewalls "have been topped out," a milestone that precedes slab‑on‑grade pours for classroom wings. He reported the classroom wing C slab had been poured and contractors held a community Kona Ice outreach event with roughly 30 to 40 attendees. At Mary Frances Wall, staff reported the pre‑engineered metal building had been delivered, curb and gutter work was about 75% complete with a connection to Palisade Drive finished, the main waterline tap was completed and all slabs on grade had been poured. Cohen noted the CMU work continues between the 1995 portion and the new construction to form rated rooms such as the warming kitchen and electrical and fire control rooms. For the Opportunity School, Cohen said footing and foundation work continued and one of the project's two slab pours had been placed; the team expected the project to be tracking for completion in June, as discussed in the meeting. He also said the site contractor cleaned a borrow/spoil area to use as a laydown zone and that a relocated dumpster enclosure would be completed before school starts. On the transportation fuel‑farm project, Cohen said three new 20,000‑gallon diesel tanks are planned and demolition was scheduled to start Aug. 25 with owner training projected Oct. 15. Board members asked clarifying questions about overnight work, traffic and neighborhood notification; staff said most work would continue during daytime hours and that they would confirm outreach to neighbors for the fuel‑farm site. Cohen defined "CMU" aloud as concrete masonry unit when asked. Ending: The board received the updates and had no formal vote; staff said remaining activities would be sequenced to minimize disruption and coordinated with schools and neighbors as needed.