Greenwood OKs short-term road closures for subdivision rebuilds and a Duke Energy pole replacement

5532907 · August 5, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Board granted temporary full closures for work on Combs Road at Ridgetop Section 1 and a Sagebriar closure, each subject to engineering-approved detour plans and a $1,000-per-day fee for overruns; Duke Energy was allowed a one-day reuse of a prior closure for a pole replacement on Aug. 16.

The Greenwood Board of Public Works and Safety on Aug. 4 approved temporary full road closures for two subdivision reconstruction projects and authorized reuse of a prior closure for a Duke Energy pole replacement, subject to conditions from city engineering.

Board members approved an 11-day closure request for Ridgetop Section 1 on Combs Road to perform pulverization, lime stabilization and stone placement. Kelsey Canary, the project representative for E and B Paving, told the board, “I am requesting roughly 11 days of a closure from August 11 to August 25 for Ridgetop on Combs Road.” Paul, a board member, said engineering supports a closure and asked that the board add enforceable conditions; the motion that passed requires final approval of the detour plan by the city engineering department and imposes a $1,000 daily fine if the closure exceeds the approved dates.

The board approved a separate closure for work tied to the Sagebriar project with essentially the same conditions and the same $1,000-per-day overrun fee; the applicant requested the closure from Sept. 3 to Sept. 17.

Separately, Ed Sturgaard of Duke Energy asked to reuse a previously approved closure to replace a remaining utility pole along North Street. Sturgaard requested one day — Aug. 16 — saying the work would be completed under the earlier closure footprint: “we’re requesting to reopen that road or reuse that existing road closure for the date of 08/16, which is a Saturday, to replace that pole.” The board granted the one-day reuse request.

The board consistently conditioned approvals on final engineering sign-off, coordination with emergency services and schools, and clear advance notice to affected residents. The fines for overruns and requirement for an approved detour plan apply to the subdivision reconstruction closures; staff indicated prior similar closures had carried comparable penalties.

The engineering department will review and sign the final detour plans before closures begin; enforcement of the daily fee for any overrun will be handled by the city.