Skull Hall struck by lightning in June; repairs await insurance scope and bid
Summary
A staff member reported that Skull Hall sustained lightning and water damage in June; ServiceMaster completed dehumidification and asbestos abatement, but the insurance adjuster must finalize a scope of work before the project can go to bid.
Get email alerts on the Facility Repairs Insurance topic
No spam. Unsubscribe anytime.
Staff member reported that Skull Hall was struck by lightning in June and that initial remediation is finished, but the project remains stalled pending an insurance adjuster's final scope of work. ServiceMaster completed dehumidification and water-damage work, and asbestos abatement has been carried out, the staff member said.
The matter cannot be sent to competitive bid until the insurer's adjuster issues a value-of-damage assessment and a written scope of work, the staff member said. The speaker said an adjuster inspected the building earlier and that staff assisted an inspector with a bucket truck to examine the cupola. That feature, the speaker said, was previously the subject of a vote to retain it.
The staff member said the adjuster had previously indicated the assessment would be ready in "a week or two," but staff have not yet received a written scope. Staff said they recently emailed the adjuster asking for a status update and have not received a reply; the file is currently "in the adjuster's hands," according to the staff member.
No dollar amounts, contractor bid timelines, or a revised construction schedule were provided in the remarks. The transcript did not specify which governing body previously voted to retain the cupola, who made the motion, or the vote tally. The staff member did not state an estimated date when bids would be solicited.
Next steps described in the remarks are administrative follow-up with the insurer and preparation to issue a scope for bidding once the adjuster provides the required documentation.