Council awards Chambers Road–Stroh Road traffic signal contract to Adeona Transportation Solutions
Summary
Council awarded a $606,456 contract to Adeona Transportation Solutions to install traffic signals at Chambers Road and Stroh Road; staff warned lead times for signal poles can be long and completion is expected in 2026.
Get email alerts on the Transportation Infrastructure topic
No spam. Unsubscribe anytime.
Parker Town Council on Aug. 4 awarded a construction contract to Adeona Transportation Solutions for traffic signal installation at the Chambers Road and Stroh Road intersection (CIP20-434) for $606,456. Engineering staff said the town solicited bids and opened four responsive proposals on July 22; Adeona submitted the lowest responsible bid. Staff recommended award and noted Adeona currently performs subcontract work for other Parker signal projects, which staff said supported their standing and readiness to proceed. The town expects a notice to proceed roughly a month after award and completion targeted for 2026; staff cautioned that long manufacturing lead times for signal poles (up to six months) drive schedule considerations. Why it matters: Chambers Road is a newly opened segment that councilmembers described as an important alternate route. Signals at this intersection are intended to manage growing traffic; staff said traffic projections and the road’s six-lane buildout justify the timing. Council action: Council approved the contract by motion on the regular agenda; the vote was unanimous. Funding for the contract is available in the project budget and staff said the bid represents roughly a 15% savings compared with the engineer’s estimate range. What’s next: Staff will issue notice to proceed, coordinate pole manufacturing lead times, and begin construction sequencing with other CIP projects; the project is expected to complete in 2026.