RDA executive director reports progress on Mill On Main, Boatworks, Pioneer Marina and other projects

5521926 · August 1, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The RDA executive director briefed the authority on multiple redevelopment projects, reporting progress at Mill On Main, Boatworks, ThetaCares and Pioneer Marina and updates on asbestos removal, demolition planning and a right-of-way encroachment issue on the Jefferson corridor.

The RDA executive director delivered a progress report on several redevelopment projects, updating the authority on near-term milestones and permitting hurdles.

Boatworks: staff reported Boatworks has opened lease applications and is screening pre-approval candidates. The authority said staff will monitor compliance with the agency's TID agreement.

ThetaCares and Pioneer Marina: ThetaCares has posted staff openings as it advances toward opening, and Pioneer Marina has submitted plans for a semi-permanent pergola that is under review for building-code compliance; the marina also proposed sand volleyball courts.

Mill On Main: staff described a recent roof and rain event that allowed water into floors between structures. Inspectors flagged the issue and the developer corrected it within a day. Staff said construction is moving and the developer is targeting completion by this fall. Dock ownership and operation remain unresolved: due to funding requirements, docks may need to be city owned and partially leased to the developer; staff said DNR permitting will take extensive time (about a year to process) and that dock leases would not be operational in phase 1.

Sawyer Street and Washington School: asbestos removal has been completed at Sawyer Street properties and staff are preparing demo work; DPW support will be used for demolition but a certified asbestos contractor is required on-site during demolition. For Washington School, bids for right-of-way, stormwater and grading were received and staff will report to the council on housing next steps.

Jefferson Corridor: inspectors found footings that extend six inches into the public right-of-way and staff said they are negotiating an encroachment agreement with the owner; staff expect to finalize the agreement within weeks and said the issue will not halt project progress.

The executive director's update included logistical notes and next steps; staff said they will return with more detailed updates as items progress. The authority set its next meeting for Sept. 17.