District delays aquatic center completion after watertightness tests find leaks; other capital projects progress with isolated issues
Summary
A watertightness test at the new district aquatic center found leaks at cold joints; staff expects resealing and waterproofing to begin and anticipates up to a two‑week delay to substantial completion.
Get email alerts on the Facilities Projects topic
No spam. Unsubscribe anytime.
District facilities staff told trustees that a recent watertightness test of the new aquatic center found leaks at cold joints and that crews will reseal the joints and apply a waterproofing membrane, work that could add up to two weeks to the substantial completion schedule.
The district’s pool designer reviewed repair options and staff said they will not rush the project and will run a repeat watertightness test after repairs and cure time. Bleachers, windows and stair railings are installed or nearly complete; landscaping and parking work remain. Staff reiterated the district’s internal target of August 8 for substantial completion but said that date could slip and that they will bridge activities from the existing facility if needed.
The replacement project for Campbell County High School is in programming and design phases; stadium schematic design is expected to start after contract language is finalized. Staff said they expect a multi‑phased approach that may include seeking additional funding from the legislature for enhancements beyond state square‑footage guidelines. The designer approved a move to 35% design for the project.
At Sage Valley, an unplanned gym floor repair was authorized after installers found buckling in part of the floor; staff estimated the repair would be paid from major maintenance and anticipated a cost in the roughly $48,000–$50,000 range, with about 17 square feet likely requiring replacement. Lakeway Learning Center demo and interior work are underway and on schedule; Rye Junior‑Senior High turf and field drainage work is in progress with completion expected for fall use. A request to the Wyoming Department of Education for lighting funding on the Rye field was denied; staff plans to shift that work to major maintenance funds.
Trustees asked about re‑testing and warranty protection; staff said they will not tile until watertightness is confirmed and warranties preserved. No formal action was taken; staff will report further updates and timing to the board.