Martin County, Stuart, Indiantown update road, drainage and bridge projects with staggered timelines
Summary
County and city engineers presented progress reports on neighborhood restoration, resurfacing, drainage and bridge projects; several projects are in design, bidding or under construction with timelines ranging from weeks to next year.
Get email alerts on the Public Works Projects topic
No spam. Unsubscribe anytime.
County and municipal public‑works staff provided a series of project status updates covering neighborhood restoration, resurfacing, sidewalks, multimodal paths and bridge work.
Keith Baker, Martin County capital projects administrator, said neighborhood restoration projects follow a three‑phase approach — drainage, utilities and then paving — and reported the Port Salerno Peninsula sewer installation was “approximately 30% complete.” He said Riverside Park (City of Stuart) is about 70% complete under an FDOT grant, Old Palm City North design is about 90% complete for resiliency work that will elevate roadways in flood‑prone areas, and the SPS Manatee Business Park drainage study is being finalized.
For resurfacing, Baker said Leilani Heights milling and resurfacing work began and is about 25% complete with anticipated work continuing into August and September; Hope Hills was in bid packaging with construction expected in the fall. Sidewalk and multimodal items included Southeast Avalon Drive sidewalk (utility coordination and last FPL pole relocations pending) and the SunTrail multiuse path design at about 60% to connect Jonathan Dickinson Park to nearby state park lands. For bridges, Dixie East Fork Creek bridge is complete and the Hobe Sound bascule‑bridge scour prevention design is at 100%; County Line Road bridge work awaits final utility coordination and Army Corps permits from FPL and AT&T.
City of Stuart utilities director Peter Koonan reported municipal resurfacing is underway on several city streets with milling and resurfacing targeted for completion by September; a major Conquistador lift‑station rehabilitation contract is being awarded with work expected to begin in September and run through March 2026. Koonan also said headworks rehabilitation at the city water‑reclamation facility is under construction with completion anticipated in January 2026, and Veterans Memorial Park upgrades are on schedule for March 2026 completion.
Village of Indiantown director Pat Nolan said Uptown roadway and drainage design funded by FDOT is complete but lacks construction funding; the village is pursuing funding for a 100‑year‑old Railroad Avenue main replacement and noted a 12‑inch looping project funded by ARPA and county funds is nearly complete.
Discussion vs. decisions: Presentations were informational. Several projects are awaiting funding, bid release or utility coordination; staff described coordination steps with FPL, AT&T and the Army Corps but reported no board action taken at this meeting.
Why it matters: Multiple neighborhood and regional transportation projects affect local travel, flood resilience and utility reliability; timing depends on funding, permitting and utility coordination.
Ending: Staff invited questions and noted upcoming bid windows and permitting milestones for several projects.