Utility contractor reports valve installations, service‑line checks and potential shutdowns for water‑main project

5516834 · July 21, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

IMAIC reported progress on the city water‑main project: crews located valve sites and measured pipes, materials are on order, tie‑ins depend on receiving special valves and some residents may face temporary shutdowns when valves arrive.

Shane Waterman of IMAIC told the council the contractor has exposed each location planned for special valves and measured existing pipe; materials are on order and the project schedule depends on those parts. Waterman said the valves are planned at intersections including Broad & Center, south of the fire station on Wind, Prairie & Third Avenue, and Bates & Third Avenue to allow crews to isolate sections during tie‑ins. Until the new valves arrive the contractor may temporarily cap mains and delay tie‑ins; Waterman said the city will notify affected residents if broader shutdowns are required for valve installation and planned tie‑ins. He reported crews have not yet found additional undisclosed water service issues beyond old galvanized service lines in some locations; where leaks are discovered the utility will contact homeowners to discuss replacement options. Waterman said rain has slowed work recently but that the contractor expects to provide a schedule within about two weeks after the materials arrive. The council asked staff to continue public notification plans ahead of any required shutdowns.