Summary

Polk County Commissioners approved an emergency contract to fully replace the roof at the Dunbar Complex after inspections found the roof saturated down to the wood deck; the court authorized a budget amendment to fund the work from the general fund.

Polk County Commissioners on Tuesday approved an emergency contract to replace the roof at the Dunbar Complex, saying infrared scans show the roof system is saturated down to the wood deck and can no longer be patched. County staff recommended full removal to the deck, inspection and repairs as needed, installation of tapered insulation to direct water to drains and scuppers, and a heavy-duty multi-layer waterproofing system.

County Judge (unnamed) and staff said the replacement is urgent to prevent interior damage. Grady Woods, the county’s new maintenance supervisor, brought the need for a full replacement to the court. Brent Hepler, representing the recommended contractor, described a 25-year warranty approach that includes on-site oversight three times a week during installation and said the vendor had performed infrared and structural evaluations that found widespread saturation.

The county received three written quotes: FW Oakland, RASUS Urethane, and Atlas Universal; commissioners recommended and approved a contract with Walton Incorporated. Commissioners also approved a motion that will require the auditor’s office to bring a budget amendment at the next meeting so funds can be drawn from the general fund to pay for the emergency work, with the expectation the county will reconcile the budget at year end.

The court approved the award by voice vote after a motion and second. No formal roll-call vote with named yes/nos was recorded in the transcript. The county noted that the project was procured through the OMNIA purchasing cooperative and staff said the vendor assumes project liability as manufacturer.

County staff and the contractor emphasized that the work cannot be deferred without risk to the building interior and that re-exposing and correctly reconnecting drains will be part of the scope. The court’s action included direction that the purchasing and auditor’s offices prepare the necessary budget amendment and documentation for the next meeting.