Public works updates: MBR startup timeline, booster pump tie‑in, Broadway rehab and multiple federal grants

AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Public works staff reported that the wastewater MBR system should be operational by September pending software integration, a new booster pump station will require a PRV before tie‑in, and multiple transportation projects — including Broadway/Division rehabilitation and several federally funded roundabouts — are moving through design and bid qualification.

Public works staff presented the utility and transportation quarterly report, giving project timelines, staffing updates and contract activity.

Jim Kelly (staff member) said the wastewater membrane bioreactor (MBR) program remains in integration and computer‑programming work; staff expect to resolve the computer issues and have the new MBR operational by September. The new PLC/SCADA installation at the water treatment plant is complete but programming work continues. The 640 booster pump station building and generator are installed and operational, but staff will not tie the booster into the system until a pressure‑reducing valve (PRV)…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans