Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Infrastructure Assessment topic
No spam. Unsubscribe anytime.
Commission approves HDR scope of work for Georgetown Lake dam assessment
Summary
The county approved a contract scope of work with HDR (consultant) for a Level 2 risk analysis and reservoir assessment related to Georgetown Lake and dam operations.
Get email alerts on the Infrastructure Assessment topic
No spam. Unsubscribe anytime.
Granite County commissioners approved on July 29 a scope of work and agreement with HDR (listed in the meeting as the consultant for a reservoir/dam assessment) to perform a comprehensive assessment, failure‑mode analysis and related studies for Georgetown Lake and its dam.
What was approved: According to staff and the consultant’s representative, the scope covers field inspections, a level‑2 risk analysis, a potential failure‑mode analysis and a final technical report. Most field work is planned for the winter-to-spring window; substantial tasks were described as occurring from the current fiscal year through next spring.
Why it matters: County staff and residents identified the HDR study as important to long-term reservoir operations, safety and compliance with licensing requirements. Several speakers said the report will help the commission and stakeholders understand risk, permitting constraints and flood/operational trade-offs.
Vote and outcome: The commission voted to approve the consultant scope and the contract; a motion to approve passed and staff were authorized to finalize the agreement.
Next steps: The consultant and county staff will finalize the contract and schedule field inspections (staff indicated field inspections would be scheduled in a May timeframe for on-site work), then deliver the draft and final reports per the contract timeline.

