Sumner County schools: bleachers, stadium work mostly on schedule; Station Camp track may lag
Loading...
Summary
Sumner County Director of Schools Dr. Langford told the board that most stadium and bleacher projects across the district are progressing and should be ready for fall, but work at Station Camp High School may not meet its first home-game timeline because heavy rain delayed paving and track surfacing.
Sumner County Director of Schools Dr. Langford said most athletic-facility projects across the district are progressing and are expected to be ready for the fall season, though work at Station Camp High School may run behind schedule because of recent heavy rain.
Dr. Langford, the district's director of schools, told the board that bleacher installation at Hendersonville and other sites was moving quickly and that a press box was being delivered. "When I pulled in Friday at 05:30 in the morning, they were unloading the aluminum. The press box should be there today," he said. He added that Portland is "done, for the most part," noting only cleanup and punch-list work remained.
The director said Station Camp was the project most at risk of delay. "We really turned the corner of Station Camp last week," he said, but added that repeated rain days slowed dirt work and the timing for laying the track surface. He explained that the track surface must cure for about 30 days after installation, and that the project needed a stretch of dry days that the site did not always get.
Dr. Langford described contingency plans if Station Camp is not ready for a scheduled home game: the team could flip a home date to another Sumner County stadium, or play the game at an alternate county venue such as Rockvale, with compensation and logistics arranged for groups providing paint, concessions and other services. "Worst case scenario, they would flip it and play it at Rockville this year, then they would come here next year," he said.
The director also discussed Gallatin High School and soccer-season preparations, saying the school must clear an area and complete dirt-and-track work before the season starts. He described infrastructure work at Gallatin that would allow adding a stadium on campus at a later date without redoing utilities and other systems.
Dr. Langford highlighted other site work: North Southern was "coming along," Hendersonville would change the skyline when finished, and Indian Lake-area work had progressed after two years of little visible activity. He also told the board that recent projects included soil replacement under tracks that had been cracking and eroding.
On cost and upgrades, Dr. Langford noted the district is installing a new track and irrigation system, saying in the meeting that the district is "also getting a $2,100,000 track and, you know, new irrigation." He cautioned that some ancillary items — concession and bathroom buildings and underground plumbing — could remain as punch-list work after the main structures are in place.
The board heard several logistical details and limitations: some turf, track and field work cannot proceed until proper dry weather windows occur; installing track surfaces requires a curing period that affects when games can be held; and moving a home game typically involves compensating outside groups that provide field painting and concessions.
No formal motion specific to construction sequencing was recorded; the discussion was part of the director's regular facilities update.
Ending: The district will monitor Station Camp progress closely over the coming weeks and use alternate venues if necessary. Dr. Langford said the district was hopeful most projects would be usable at kickoff but that Station Camp remained a watch item.

