Council approved a change order to add $8,000 to the Pecan Avenue drainage contract for engineering a replacement bulkhead tied to Magnolia Beach and drainage restoration work; council was told bidding could begin in August and construction in October–November.

Public Works staff asked the council to approve a change order increasing the Jay Consulting contract by $8,000 to design a replacement bulkhead at the downstream end of the Pecan Avenue drainage project. The bulkhead had been found to be in very poor condition during coordination between the Pecan watershed drainage project and the Magnolia Beach restoration.

“Part of the drainage project is rerouting this drainage to actually employ the bulkhead that's immediately south of Pier Avenue so that we, 1, get the discharge off the beach…and, 2, clean all that up,” the public works presenter said. Engineers determined the existing bulkhead is in bad shape and that redesign and integration into the drainage plans were needed to avoid future problems.

Staff told the council the drainage design is ready, the bulkhead engineering could be completed quickly, and the team was aiming to go to bid in August with construction targeted for October–November. The council approved change order number 1 for professional engineering services for the Pecan Avenue water management project and awarded the amendment to Jay Consulting with a not‑to‑exceed cost of $8,000, bringing that contract's total to a new amount described in the meeting materials.

Ending: Council approved the $8,000 contract amendment; staff will proceed to finalize design, advertise for bids, and aim for construction in the fall months.