County says $4.5 million set aside for 2 Mile Road drainage; design work underway
Summary
A resident asked the commission for help with severe yard and house flooding on 2 Mile Road in Grand Bay; commissioners said $4.5 million in PAYGO funds has been dedicated for drainage design and paving and that engineering design work is underway.
Get email alerts on the Infrastructure Drainage topic
No spam. Unsubscribe anytime.
Monica Malone told the Mobile County Commission on July 28 that water is backing up into her elderly mother’s house on 2 Mile Road in Grand Bay and asked for a timeline for repairs.
County officials responding at the meeting said the county has dedicated about $4.5 million from the PAYGO program for a drainage and paving project on 2 Mile Road in the area Malone described. Commissioners and county engineers said a drainage design is currently underway and that the county did not want to pave the road until the drainage design is complete, because paving without designed drainage could worsen runoff onto adjacent properties.
Kim, the county engineer, confirmed the design is in progress and staff will provide frequent updates; staff said a community meeting will be scheduled as design advances so residents can provide input.
Discussion versus decision: the meeting did not authorize new funding at this session; commissioners said funding has been dedicated previously and that engineering design and subsequent construction are next steps. Staff advised residents to make post-meeting contacts for regular updates.
Clarifying details: commissioners said the project’s largest cost component is drainage work and that the money was set aside in the 2024 PAYGO allocation and additional funds are planned to complete the paving after drainage is addressed. Staff invited the resident to meet after the meeting for contact information and to receive future project updates.
What’s next: the county engineer will continue design work, the county will schedule a community meeting when plans are further along, and staff will keep the resident informed about design and construction timelines.