Flatwoods Park contract increased and completion date extended after prefab restroom delay

5493348 · July 25, 2025

Get AI-powered insights, summaries, and transcripts

Subscribe
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Board approved Change Order No.1 with Strausser Construction adding $7,875 to the Flatwoods Park contract and moved the substantial completion date from July 31 to Dec. 1 because a prefabricated restroom unit is delayed in production.

The Monroe County Board of Commissioners approved Change Order No. 1 for the Flatwoods Park project, increasing the contract by $7,875 and changing the substantial completion date from July 31, 2025, to Dec. 1, 2025. The change order pays for items including PVC drain pipe, repairs to a basketball goal, and additional topsoil and grading around the basketball/pickleball court. County staff said the restroom for the park is a prefabricated unit being manufactured in Ohio and that production-line scheduling is delaying delivery. "We're at the mercy of being in line for everyone," a county project representative said when explaining the date change. Commissioners clarified a prior math error in agenda materials that affected the stated original contract total; staff confirmed the exhibits and change-order amount were correct and that the corrected total contract value is $458,075. The board recorded the correction on the record and confirmed the previously approved change order amount remains $7,875. The motion to approve the change order and the new substantial completion date passed by voice vote, 2-0. Staff said the parks department will pay the additional change-order cost and will continue to monitor delivery schedules for the prefabricated restroom.