Board approves $1.67 million change order to SJEC water treatment plant expansion, adds 30 days

5491198 · June 25, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Commissioners approved change order No. 1 for the SJEC water treatment plant Phase 3 expansion: an increase of about $1.666 million (roughly 6.1%), a 30-day time extension and substantial work to add a well house and well field capacity adjustments.

The Saint Joseph County Board of Commissioners on June 24 approved change order No. 1 for the SJEC water treatment plant Phase 3 expansion, increasing the contract by approximately $1,666,202.45 (about 6.1%) and adding 30 calendar days to the project schedule. Substantial completion was moved to Sept. 29 with a final completion of Nov. 26, according to staff comments.

Skye…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans