Board OKs three change orders that increase downtown streetscape contract

5483939 · July 15, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Board of Works approved three change orders increasing the Downstone Street downtown streetscape contract by $113,613.45, citing additional mobilization, unforeseen underground work and material-size changes; two payments will come from the Redevelopment Commission (RDC) and one from sanitary/stormwater funds.

The Board of Works voted to approve three change orders to the Downstone Street downtown streetscape project, increasing the contract by $113,613.45.

Engineering Department staff said the adjustments reflected work extending into 2025, unexpected underground construction delays and a materials change to match previously installed downtown planters. "Change order 2 was for an additional mobilization charge in the amount of $41,267, just based on work extending into 2025," Engineering Director Max said. "Change order 3 was related to underground work construction and unforeseen delays related to that in the amount of $49,152. And lastly, change order number 4 was for material costs only, just swapping out the planters to a bigger planter size consistent with what our parks department has installed previously in the downtown area."

City staff told the board that change orders 2 and 4 will be paid from the Redevelopment Commission (RDC) budget and that change order 3 will be paid from sanitary sewer and stormwater funds. "Change orders 2 and 4 are to be paid from RDC and has received RDC approval. Change order 3 is to be paid from sanitary sewer and stormwater. Obviously, we received utility board approval," Max said.

The board approved the recommendation unanimously.

The project previously received RDC oversight; the board did not detail a revised overall contract total in the meeting beyond the increase tied to the three change orders.