Staff reports progress on police building interior and dispatch console at monthly construction update
Summary
Staff gave a July construction update on the city’s police building: ceiling grid and lighting installed in parts of the interior, dispatch console under construction, new catwalk above the council chamber and exterior awning work progressing.
Get email alerts on the Capital Projects Building topic
No spam. Unsubscribe anytime.
City staff provided a construction update on the police and municipal building project, showing interior progress and upcoming items as part of a monthly update.
A staff member identified as Aaron presented photos and described interior work: ceiling grid and light fixtures installed in parts of the police department, a new dispatch console desk under assembly, and pendant lighting still to be installed in the council chamber. He showed a photo of a catwalk above the council chamber that will aid cable runs and maintenance access.
On the administrative side, Aaron said ceilings and carpeting have been installed in some areas and that the exterior work — weather stripping at the front and a new front awning — is taking shape. Staff answered a brief question from council about whether dispatch had moved back; the update indicated the new dispatch arrangements are forthcoming.
No formal council action was taken on the building update; staff reported the work in a routine project-status briefing and fielded questions from council.