Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Water Infrastructure Construction topic

No spam. Unsubscribe anytime.

Hampstead officials say pipeline work expected in August; bids for water treatment plant may slip

5466036 · July 24, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Town staff told the Planning and Zoning Commission that pipeline construction for a town water system project is expected to begin in early August along Shiloh Road, and that bids for two water treatment plant contracts are set to open in early August but likely will be extended while addenda are approved by the state.

Town staff updated the Hampstead Planning and Zoning Commission on July 23 that pipeline construction for the town'wide water project is expected to begin in August and that water-treatment plant contract bidding is underway but may be delayed.

The zoning administrator said work will start along Shiloh Road, opposite Hampstead Elementary, and that silt/salt fencing will go up in the coming week. "We're very close to breaking ground with pipeline construction," the administrator said, adding crews hope to start tearing up the road in the second week of August and to be finished on that segment before school starts.

Timeline and contracts - Pipeline: the town expects to begin pipeline work in early to mid-August; the zoning administrator said the longest portion of pipeline construction could take up to one year but that he anticipates the Shiloh Road segment will be completed in seven to eight months. - Treatment plant bids: two contracts are planned'one covering North Carroll Farms and Shiloh facilities and a second for the Dairy and Hampstead Valley facilities. Bids were scheduled to be opened on Aug. 4 but staff said the deadline will likely be extended while a large number of bidder questions are answered and addenda are approved by MDE.

Public outreach and other projects - Town hall: staff announced a town hall meeting on July 31 at 6:30 p.m. at Hampstead Town Hall to review the project plan and the two-year construction timeline. - Roberts Field Stormwater Management Pond: staff reported a well-attended town hall on the Roberts Field pond project; county staff (Claire Hurt and Janet from Resource Land Management) are reviewing resident requests and will discuss possible design changes with the project engineer. - Tractor Supply concept plan: the zoning administrator said Tractor Supply expects stormwater concept approval this week and will return in August for Planning Commission consideration.

Why it matters: town staff said the pipeline work will cause the most traffic disruption and public inconvenience during construction; treatment-plant work will be less visible once pipelines are in place. The bid packages are large'the zoning administrator said each contract's paperwork exceeds a thousand pages'and will require time to process and respond to bidder questions.

No formal action was required on these updates; the commission took the briefing and later approved related items on the agenda where applicable.