Council awards Dorado Drive reconstruction bid for about $1.34 million
Summary
The city awarded the lowest responsive bid for full-depth reconstruction of Dorado Drive (from Fother Road to Mission Boulevard), a project expected to rebuild roughly 25,000 square yards of roadway and address drainage issues.
Get email alerts on the Street Reconstruction topic
No spam. Unsubscribe anytime.
The Odessa City Council voted unanimously July 22 to award a bid for full-depth reconstruction of Dorado Drive from Fother Road to Mission Boulevard.
Public works staff (identified in the meeting as Ron) told the council the bids for the project were opened July 9 and three responsive bids were received. Staff reported the lowest responsive bid was "$1,341,962.75" and recommended awarding to that bidder. The project was described as a full-depth reconstruction covering approximately 25,000 square yards (about 0.8 linear miles) and will include curb and gutter replacement, concrete valley repairs and alley approach installations to improve roadway drainage.
Staff said the project is within the budgeted amount, that Newton Engineering was the design consultant, and recommended reserving a 20% contingency. The project schedule presented anticipated completion within 100 working days.
Council discussion included a request from Councilman Mitchell to avoid removing certain landscaped medians funded by the Mission Homeowners Association and instead to adjust irrigation and bubblers; Mitchell asked the council to include that caveat in the approval. Councilman Mitchell moved to approve the award with that caveat; Councilman Canell seconded. The motion passed unanimously.
The public record did not include the vendor company name beyond the staff’s “lowest responsive bidder” phrasing, and no specific contract number or signed contract was presented during the meeting.