Board receives June update on Homestead High School additions budget
Summary
Board staff reported $2.9 million in June expenditures for Homestead High School additions and renovations, bringing total project costs since inception to $187,513,272 with $7.2 million in interest and earnings.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
The School Board on July 8, 2025 received an update on the Homestead High School additions and renovations budget. Board staff reported that the project incurred about $2.9 million in expenditures in June. Since the project began, total expenditures have reached $187,513,272, and the project has recorded $7,200,000 in interest and dividends. Randy Libby presented the figures and offered to answer questions. The presentation was an informational budget update; there was no formal action or vote tied to the report during the meeting. The board packet contains spreadsheets and category breakdowns that Libby referenced for the monthly update. Board members did not direct new actions tied to the June budget report during the discussion; Libby closed the item by inviting questions and moving on to the next agenda item.