Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Energy Wind Projects topic

No spam. Unsubscribe anytime.

MidAmerican Energy says turbine-component offload for Page County project planned for August

5464806 · July 23, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

A MidAmerican Energy representative told county officials the project is on schedule for component offload in August but warned weather or other delays could change that timetable.

A MidAmerican Energy representative identified only as John told the meeting that foundation-concrete work is underway and that the company was preparing to begin turbine-component offload in the county in August.

John said foundation concrete pouring in Page County is “really into the thick” and that work in a neighboring area was nearly complete, allowing crews to focus on Page County. “As of right now, yeah, that August is when we'd be looking at turbine component offloading,” he said. He added that the schedule could shift because of weather or other delays and that he would provide updates if the timeline changed.

No permits, road-use agreements or offload locations were described at the meeting and no formal county approval or vote on the project was recorded.