Board awards night‑work contract to pave Elm Street business district for $169,880
Summary
The Board of Selectmen approved a $169,879.75 contract with Burns Construction, plus a 10% contingency, to mill and repave the Elm Street business district in August with night work.
Get email alerts on the Infrastructure Paving topic
No spam. Unsubscribe anytime.
The Board of Selectmen unanimously approved a contract with Burns Construction to mill, reclaim and repave the Elm Street business district (Main Street to Park Street) in an overnight operation. The low bid was $169,879.75; the board authorized a 10% contingency, bringing the total project authorization to $186,879.75.
Town engineers and public‑works staff told the board they solicited six contractors and received two bids; Burns submitted the low bid and is slated to perform night paving starting in early August to minimize disruption to businesses. The work will be performed overnight, generally between approximately 9 p.m. and 5–6 a.m., consistent with previous downtown paving operations.
The board asked about follow‑up steps including striping and the schedule to install decorative crosswalks. Public‑works staff said striping will follow a one‑week cure period after paving and that the town has reached out to the subcontractor who installed decorative crosswalks on the library plaza to schedule the stamped crosswalk work during the same construction season.
The contract award is funded from the town’s pavement management program.