Council approves Oshkosh Street roadway plans and preliminary assessments; crosswalk, lateral assessments cleared for construction
Summary
The Common Council approved roadway plans for Oshkosh Street and recommended preliminary special-assessment resolutions covering sanitary and water laterals. Board of Public Works recommended related designs for Ashcroft Street, and staff warned that a state grant of roughly $2.02 million could be jeopardized if grant requirements are not met.
Get email alerts on the Public Works Roads topic
No spam. Unsubscribe anytime.
The Common Council voted to approve roadway plans for Oshkosh Street and to recommend preliminary special-assessment resolutions covering sanitary and water lateral work, council records and Board of Public Works reports show.
The action follows multiple Board of Public Works meetings in which Director of Public Works Garski reviewed engineers’ block-by-block plans for Ashcroft Street and Oshkosh Street and discussed crosswalks and stormwater, alignment and intersection standardization. "There will be a crosswalk on Oshkosh Street at Wolf River Avenue intersection. We are working through grade issues, but we will have a receiving area on the east side of the intersection," Director Garski said during a December 9 Board of Public Works meeting.
The Board recommended the roadway plans for Oshkosh Street at its special meeting; the board reported the motion to recommend the roadway plan designs for Oshkosh Street carried by an 11-0 vote in committee and the subsequent council vote carried 10-0. A separate Board of Public Works motion to postpone gathering additional information about a crosswalk at Wolf River Avenue carried 7-2 at an earlier meeting while the committee continued engineering review.
Nut graf: The approvals clear engineering and assessment steps needed to move a multi-block reconstruction into 2025 construction plans, while also resolving where property owners will be assessed for sanitary and water lateral replacements and where the city will absorb work in the public right-of-way.
Most substantive details: The preliminary resolution for assessments covers sanitary laterals from the house to the main (including Y connections) and the public portion from the main to the city right-of-way; the private portion from the right-of-way to the building remains the property owner’s responsibility unless the property owner signs a waiver allowing the city contractor to do the private-side work. The resolution also covers water-service lateral replacement if needed. The board specifically noted there will be no assessment for curb and gutter, driveway aprons or the road surface as part of this preliminary resolution.
At the December 9 Board of Public Works meeting, Garski warned that grant funding could be at risk if project standards in the state municipal agreement were not followed; the board reported the funding figure as $2,021,812.50. The committee also approved roadway plans for Ashcroft Street, saying most changes are for "standardization of the roadway and creating better visualization and equalized intersections where they are compromised by offsets."
Council and board actions: Motions recommending the roadway plan designs and preliminary assessment resolution were carried in committee and approved by the council. The transcript shows the Board recommended the preliminary resolution for assessments and later the council approved the roadway plans and preliminary assessment resolutions; individual council members cast ballots but the formal roll calls in the transcript record only the tallied outcomes (committee votes 11-0 and 10-0 at council for the listed motions).
Discussion versus decision: Board discussion included requests from residents to slow traffic and specific safety concerns about a crosswalk at the Wolf River Avenue intersection, questions about receiving sidewalks and grading, and counsel to verify grant wording so funding would not be compromised. Formal direction included the recommendation to council on the roadway plans and the approval of a preliminary special-assessment resolution that specifies what will and will not be assessed.
Ending: The Board and council directed staff to finalize engineering details and to coordinate grading and crosswalk design so the project can proceed in 2025, with further sign and school-zone considerations to be discussed at future meetings.