H‑Barn schematic design estimate nearly doubles earlier projections; city to weigh scope and funding

5455775 · July 23, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Schematic design for restoration of the historic H‑Barn returned an estimated total project cost of about $14.3 million; staff identified options to reduce the budget to roughly $10.4 million and outlined possible grant and lodging‑tax financing but said roughly $3.5–7.5 million remains to be found depending on final scope.

City manager staff presented a schematic‑design cost update for the H‑Barn restoration and renovation project on July 21 and told council the current construction and site estimate is about $14.3 million, substantially higher than earlier, lower estimates.

The estimate includes building work, site improvements, professional design and permitting fees, cultural resources studies, allowances for testing and inspection, furnishings, contingencies, bonds and insurance,…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans