Wood County supervisors approve plan to upgrade meeting-room audio and video, request $75,000 appropriation
Summary
The board reviewed a proposal from Lee Hartman for new microphones, cameras and an FM overflow transmitter to serve the parking lot, with an estimated equipment cost of $69,224.70 and a recommended appropriation of $75,000 to cover incidentals; the board moved to proceed and a roll call was requested.
Get email alerts on the Av Upgrade topic
No spam. Unsubscribe anytime.
County staff and supervisors discussed a proposal to replace and upgrade the audio-visual system in the Board of Supervisors meeting room, including new microphones, cameras, relocated control room space and an FM transmitter to provide overflow audio coverage to the parking lot.
Mr. Angus, a staff member who met with the county IT representative, described the proposal from Lee Hartman of Roanoke as a comprehensive solution and said the vendor’s price came in about $30,000 below the state contract price. He said the equipment quote totaled $69,224.70 and recommended a budget appropriation of $75,000 to cover incidentals and potential changes during installation. He estimated 3–4 weeks to receive equipment and about a week on site for installation, barring backorders.
Mr. Angus noted that the FM transmitter would cover only the parking lot and would be intended for overflow during public hearings or for accessibility purposes rather than general public broadcast. Supervisor Barnett moved to proceed with the project and to amend the budget to appropriate $75,000 to account code 1101470015 (board supervisors’ furniture/fixtures); Supervisor Lawson seconded the motion. The chair called for a roll call vote.
Board members asked clarifying questions about the vendor’s prior work with local staff and the ability to livestream proceedings directly to the county YouTube channel. Staff said county personnel (Mr. Hankins and Mr. Patrick) had previously worked with the vendor and that the new system would provide direct streaming capability.
If approved and scheduled, staff estimated installation would take about a week after equipment arrival. The board did not receive public comment on the AV item during the discussion recorded in the transcript.