Committee approves final change order for Kenilworth stormwater project; figures in meeting vary
Summary
Council approved the final change order and final invoice for the Kenilworth stormwater project. Presenters said the project finished roughly 9.85% over the original bid but remained under a 10% threshold and about 1.8% over the budgeted amount; the recorded change order figure varied in discussion.
Get email alerts on the Kenilworth Stormwater Change Order topic
No spam. Unsubscribe anytime.
The finance committee on July 21 approved the final change order and final invoice for the Kenilworth stormwater project, concluding the multiyear construction item on the agenda.
Council Smith, who presented the update, said the contractor disturbed more area than anticipated, requiring additional sodding, tree work and lowering of modified grama inlets after a significant May rain event. Smith said the project’s final invoice left the total about 9.85% over the original bid — and therefore under the committee’s 10% change-order threshold — and roughly 1.8% over the budgeted amount.
Smith also reported the city had received a $150,000 reimbursement from ADEM. During discussion, committee members and staff referenced differing line-item figures in the paperwork: at one point a change order amount of $16,818 was mentioned; later a figure of about $26,501 and “some cents” was put forward for approval. The committee approved the motion to accept the final change order as presented.
Motion and vote: Councilor Harden moved to approve agenda item O20225; Mr. Brandt seconded. The committee approved the change order 3-0.
Status: The contractor’s final invoice and change order were approved and the project will be removed from future committee agendas after the council’s formal action.