Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Street Construction topic
No spam. Unsubscribe anytime.
Board approves Switlick and Sons change order and $519,147 pay estimate for Fulton Street project
Summary
The Board of Public Works approved a $10,200 change order and a $519,146.97 pay estimate for the Fulton Street, First Street and Second Street construction project carried out by Switlick and Sons.
Get email alerts on the Street Construction topic
No spam. Unsubscribe anytime.
The Board of Public Works on July 23 approved a $10,200 change order and a pay estimate totaling $519,146.97 for the Fulton Street, First Street and Second Street construction project carried out by Switlick and Sons. A board member moved to approve both items and another member seconded; both motions were approved by voice vote.
The change order covered two items: replacement fittings for the water main and upsizing sanitary manholes. A staff member explained the project encountered shallower-than-expected water at an intersection that conflicted with the planned sanitary sewer, requiring the contractor to drop the water main and install fittings (two 45-degree bends and two 22.5-degree bends) priced at $1,800 each. The project also removed two planned 4-foot-diameter sanitary manholes (cost removed $12,000) and added two 5-foot-diameter manholes, with a net increase of $3,000. Combined, the fittings and manhole adjustments produced a $10,200 recommended change order.
Separately, the board approved pay estimate number 3 for Switlick and Sons for work to date, in the amount of $519,146.97, which the transcript indicates was recommended by the project inspector, Kurt Gabor. The approval was recorded by motion and voice vote.
Discussion: Staff described the change order as necessary because of an unanticipated water-main conflict and pipe-size requirements that affected manhole specifications. There were no recorded dissents in the transcript and no amendments to the change order were proposed during the meeting.
Implementation and next steps: The transcript shows the board approved the recommended change order and pay estimate; no further directions or follow-up tasks were stated on the record.

