Drainage board approves $21,928.90 change order for Loffner tile project
Summary
The Boone County Drainage Board approved change order No. 2 for the Loffner (Loughmere) drainage project to pay the contractor $21,928.90 to connect several previously unknown drain tiles encountered during construction.
Get email alerts on the Construction Change Order topic
No spam. Unsubscribe anytime.
The Boone County Drainage Board on July 21 approved change order No. 2 for the Loffner (Loughmere) drainage project, authorizing payment of $21,928.90 to Morphy Construction to connect tiles that were discovered during construction. The board voted to approve the change order during the meeting; the motion passed unanimously.
The change order covers work to connect two 6-inch tiles, one 8-inch tile on the east side of the project and an 18-inch tile on the west side that were not identified during design. County staff said the field connections were completed earlier in the year and the change order reflects the negotiated cost with the contractor. Final project completion and final cost reconciliation will occur later in the fall after seeding and other closeout items are finished.
Board members asked if there were questions; none were raised before the motion to approve. County staff identified the contractor involved as Morphy Construction and said the change order is to allow payment for work already completed.
The action will enable the county to pay the contractor now, with a final reconciliation to be presented after seasonal closeout activities are complete.