Board ratifies $1.61 million partial payment for Oakland CSO tank construction
Summary
The Board ratified partial payment request No. 3 of $1,609,360 to Selj (Sal to?) Construction from an SRF loan for work on the Oakland Project B CSO tank.
Get email alerts on the Infrastructure Water topic
No spam. Unsubscribe anytime.
The Elkhart Board of Public Works ratified partial payment request No. 3 for $1,609,360 to Selj Construction from State Revolving Fund (SRF) loan WW24182006 for construction on the Oakland Project B combined sewer overflow (CSO) tank.
Jason Simnick, project manager, reported the contractor was working on the tank, wet well and CSO 37 bypass chamber and that construction was progressing. A ceremonial groundbreaking was scheduled for the tank site; Simnick said at least one wall had been poured to show progress.
The board took a voice vote and ratified the payment. Simnick said the project is moving along and that the work includes deep excavation and large concrete structures.
The SRF loan number and partial payment were recorded in the meeting record. The board did not attach additional conditions to the ratification during the session.