Council awards 40 Second Street mill-and-overlay contract to Simon Contractors for $624,237.50

5441938 · July 23, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council awarded the 40 Second Street Mill and Overlay Project to Simon Contractors for $624,237.50; work is scheduled to start Aug. 4 and take about 15 calendar days.

The Scottsbluff City Council awarded the contract for the 40 Second Street Mill and Overlay Project (Avenue I to West City Limits; Fifth Avenue to East City Limits) to Simon Contractors for $624,237.50, below the engineer's estimate of $672,000.

Doug Onder of Public Works said the city received a single bid from Simon Contractors and that the contract is scheduled to begin Aug. 4 with a 15-calendar-day completion window. Onder noted that tie-ins for a cemetery sewer connection will require one sewer crossing under the street at Hilltop where a manhole exists; the sewer work will not require replacing the full length of the road.

Council members had no further comments and approved awarding the bid.