District outlines Wright Brothers EMS site work, electrical schedule and tree removal concerns
Summary
Staff provided a status update on the Wright Brothers EMS project: anticipated permit application in August, phased electrical work beginning at the middle‑school annex, temporary fencing and tree removal; trustees asked about shade replacement and pavilion options where trees will be removed.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
District staff updated the board on the Wright Brothers EMS project timeline and site work. Staff said the anticipated permit application date is August 1, temporary fencing and initial removal work would be in place and Phase 1 would focus on electrical infrastructure with work starting at the middle‑school annex where power capacity is available.
Staff warned that final costs remain contingent on code review and feedback from the permitting authority; the project team prefers to wait for final code confirmation before committing to a fixed cost. The meeting packet lists a plan to install temporary fencing and complete three specific removals by mid‑August; staff said Idaho Power must still install or relocate a transformer and the district is dependent on the utility’s schedule for that work.
Trustees asked about tree removal in a shaded lunch area and whether new shade structures or a pavilion could be provided in place of trees where underground electrical work will prevent replanting. Staff said they would explore pavilion options similar to existing playground pavilions and noted that students rarely use the shaded fenced area at lunch in recent years because of supervision patterns.
The board requested staff provide follow‑up on tree replacement alternatives and confirmed the schedule expectation that electrical installation would begin as soon as permits are issued and Idaho Power completes transformer work. No formal action was required; the item was informational, and staff will return with updates once permits and utility scheduling are confirmed.