Board approves change order that reduces Hohman Phase 1 costs by $211,968.97
5437207 · July 22, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.
Summary
The Hammond City Board approved Change Order No. 25 for the Hohman Avenue Phase 1 project, which reduces the contract by $211,968.97; the board directed staff to repurpose returned funds for other projects.
The Hammond City Board approved Change Order No. 25 for the Hohman Avenue Phase 1 project, which adjusts bid items to final quantities and results in a net…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans