Board approves change order that reduces Hohman Phase 1 costs by $211,968.97
Summary
The Hammond City Board approved Change Order No. 25 for the Hohman Avenue Phase 1 project, which reduces the contract by $211,968.97; the board directed staff to repurpose returned funds for other projects.
Get email alerts on the Public Works Change Order topic
No spam. Unsubscribe anytime.
The Hammond City Board approved Change Order No. 25 for the Hohman Avenue Phase 1 project, which adjusts bid items to final quantities and results in a net decrease of $211,968.97. The adjustment was submitted by American StructurePoint and presented to the board by staff. Board members noted that a decrease in the contract balance returns money to the city for repurposing on other projects. A board member moved to approve the change order; the motion was seconded and carried by voice vote (ayes). The board recorded the approval and instructed staff to note the returned funds for reallocation in future project planning.