Board approves $3,500 change order to remove tree on Maywood Water and Gas project; extends contract 50 days
Summary
The board approved Change Order No. 2 for the Maywood Water and Gas project, adding $3,500 to the Argo Construction contract to remove a large tree in the work zone and extending the contract completion date by 50 days to July 25, 2025.
Get email alerts on the Utilities And Infrastructure topic
No spam. Unsubscribe anytime.
The Olive Branch Board of Aldermen approved Change Order No. 2 on the Argo Construction Corporation contract for the Maywood Water and Gas project, adding $3,500 to the contract and extending the schedule by 50 calendar days.
City staff summarized the change order during the meeting: the $3,500 increase covers removal of a large tree located where water and gas infrastructure will be installed. The approval raises the contract amount from $4,217,682.25 to $4,221,182.25 and sets a new completion date of July 25, 2025.
Alderman George Collins moved for the change order; the motion was seconded and the board approved the amendment by voice vote. Staff indicated the additional time is to accommodate the tree removal and associated work on the Maywood project.
The board did not discuss additional funding sources during the motion; record notes the additive amount and extension for the specific contract as presented.