Public works outlines upcoming paving and curb work on several Saint Francis streets
Summary
City public works staff reported asphalt paving scheduled next week for Pennsylvania, Bombay, Elizabeth, Tripoli and Alabama streets and described Phase 2 curb removal and pulverizing work on Stark, Waterford, Hately and Bombay.
Get email alerts on the Street Repairs topic
No spam. Unsubscribe anytime.
City public works staff provided a monthly update on the street improvement program, including a schedule for asphalt paving and related curb work.
Why it matters: Street repairs and repaving affect daily traffic, parking and property access for residents on the listed streets; the city said it is communicating directly with affected households.
Details provided: Staff reported asphalt paving is scheduled next week on Pennsylvania, Bombay, Elizabeth, Tripoli and Alabama. Phase 2 activities with contractor Stark include curb removal and pulverizing on Waterford, Hately and Bombay, with curb pouring expected later in the week.
Public notification: The update stated project notices were hand‑delivered to residents on the affected streets and that public works plans to provide weekly updates so residents know what to expect.
Action and timing: No council motion was required; the report described contractor scheduling and short‑term construction milestones. Staff also noted the city moved to reopen other phases of the program and is coordinating pour schedules.
Ending: The department head concluded the update and the meeting moved on to other department reports.