District facilities update: asbestos abatement finished at Northwest; HVAC and chiller work ahead of schedule
Summary
District facilities staff reported on July 16 that asbestos abatement at Northwest School is complete and flooring work is under way; rooftop HVAC units and ductwork installations continue at Southwest and Southeast campuses, and painting at Northwest is being evaluated for a later bid.
Mr. Hennessy, a district facilities staff member, told the Board of Education that asbestos abatement at Northwest School finished faster than expected and that flooring contractors were "flying through" the work, allowing a staged return of materials stored in shipping containers. "The asbestos abatement went spectacularly," Hennessy…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat