Red River reroute set for July 23; diversion construction nears key milestones
Summary
Board was told the Red River reroute will occur July 23; inlet and wild rice structure turnover now expected in October; multiple bridges and channel excavation approaching completion.
The Metro Flood Diversion Authority board was told June 26 that the planned reroute of the Red River is scheduled for July 23, with construction activities on the reroute beginning early that morning and a public ceremony expected before noon.
The reroute and related work are central to preparing the diversion to operate: Carrie, project staff for the diversion authority, said, “The reroute of the Red River has been scheduled for 23 July. That's a solid date. I'll be sending you all a save the date, probably…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat