Construction crews have put miles of pipe in ground; board reviews draft 2025–27 work plan
Summary
Project contractors have completed pipeline and structure work in several reaches and the board reviewed a draft $273 million biennium work plan that would fund ~24 miles of additional pipe and site work for a water‑treatment facility if the board authorizes Series F financing.
Kip Cobar, providing the construction update, said contractors have completed major pipeline and discharge structure work in multiple contracts and that crews have begun filling and hydrostatic testing on Contract 5B.
Cobar said Contract 5D has installed 6.3 miles of the 10 miles planned, 5B has all pipe in the ground and is in restoration, 5C has 3.7 miles in and is…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat