Committee approves replacement of outdated boilers at North Topeka wastewater plant

5416735 · June 17, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The committee approved a capital project to replace the outdated boiler/heat system at the North Topeka Wastewater Treatment Plant so staff can meet winter operation needs; staff said the existing system likely will not last another year.

The Public Infrastructure Committee on June 17 approved moving forward with a capital project to replace the boiler system at the North Topeka Wastewater Treatment Plant.

Utilities staff told the committee the plant’s existing system — described as a heat pump and “templifier” — is extremely outdated and has required extensive maintenance. Staff said they “do not believe that it is going to make it another year” and proposed replacing the existing equipment with two more efficient boilers to ensure reliable winter operation.

Design is complete and staff said they do not expect long lead‑time delays for the equipment; they indicated construction should be completed before winter. Councilwoman Michelle Hoefer moved to approve; Councilwoman Sylvia Ortiz seconded. The committee voted 2‑0 in favor.