Council adopts contract to design Well 1 pump replacement
Summary
The Shelton City Council adopted a resolution authorizing an on-call A&E work order with Grama Osborne Incorporated to design replacement for Well 1 pump and add variable frequency drives; the council approved the measure unanimously.
Get email alerts on the Water Infrastructure topic
No spam. Unsubscribe anytime.
The Shelton City Council on July 15 adopted a resolution authorizing the city manager to execute an on-call architectural and engineering work order with Grama Osborne Incorporated to design the Well 1 pump replacement project.
The action matters because the existing Well 1 pump dates from 1989 and council and staff said the replacement and installation of variable frequency drives (VFDs) are intended to increase pump life expectancy, accommodate future development and reduce long-term operating costs.
Public Works Director Aaron Nicks told the council the city has budgeted $180,000 for the Well 1 pump replacement and that the staff proposes to spend about $70,000 for engineering and electrical design work by Grama Osborne Incorporated. He said VFDs will “help your pump ramp up and ramp down very slowly,” which reduces wear and extends equipment life. The packet staff provided to council lists the existing pump placement year as 1989.
There was no public comment on the item. After brief remarks expressing appreciation for the upgrade, a council member moved to adopt Resolution No. 1390-0625 and another council member seconded. The motion passed with the council saying "aye" and the mayor declaring the motion carried; no roll-call vote tally was recorded in the meeting transcript.
Staff and council said the design work will confirm pump sizing, casing compatibility and the electrical requirements needed to install VFDs. Aaron Nicks said the work order will include the engineering to verify the new pump fits the existing well casing and the electrical modifications required.
The resolution authorizes the city manager to execute the work order; council members asked staff to continue monitoring water needs and to account for future growth in project sizing decisions.
Resolution: Resolution No. 1390-0625 authorizes the city manager to execute an on-call A&E consultant pool work order with Grama Osborne Incorporated for the design of the Well 1 pump replacement project.
Implementation: Staff will proceed with the engineering contract and return any required construction contracts or purchases to the council for separate action as needed.