County withholds $4,000 on garage HVAC contract after unit failed to restart in generator test
Summary
County staff said they are withholding $4,000 of final contract payment for a garage HVAC unit after a generator test showed the unit did not restart; staff asked for a six‑month warranty on that issue before releasing funds.
Get email alerts on the Contract Payments topic
No spam. Unsubscribe anytime.
County highway staff told the County Highway Committee on June 17 that they are withholding $4,000 of final contract payment on a garage expansion project because one HVAC unit failed to restart after a generator test.
Why it matters: staff said the contractor requested release of the $4,000, but staff want a six‑month warranty covering the specific failure mode in which the unit does not restart after a power loss before they will release the funds. Staff said the unit had been operational for roughly six months, and that after a generator test the unit failed to come back online, prompting additional testing and email exchanges among the project team.
Staff said the county will keep the $4,000 withheld until the contractor either provides the requested six‑month warranty for the specific restart issue or the matter is otherwise resolved. No formal vote was taken; staff said they will continue monitoring the issue and correspond with the contractor.