Committee approves soil-boring contract for proposed LEC site

5408527 · July 14, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The committee voted to approve a contract with InterTech, DSI, to perform geotechnical soil borings at the proposed Law Enforcement Center site; members discussed scope, timeline and optional testing.

PORTAGE COUNTY — The Portage County Building Committee voted to approve a contract with InterTech, DSI, to perform geotechnical soil borings at the proposed Law Enforcement Center (LEC) site, the committee confirmed at its meeting.

The work approved will include subsurface exploration, groundwater-level reporting, recommendations for foundation options and design parameters, estimated foundation settlement and recommendations for interior floor slabs, according to the discussion recorded at the meeting. The committee discussed the contractor’s ability to meet the project timetable and noted the contractor was the lowest bidder who could deliver within the required schedule.

The committee heard that the bid process produced multiple offers. “We had 6 other bidders,” said Speaker 3, Project manager, summarizing the procurement. Speaker 3 described the expected deliverables: “The report will bring back groundwater levels, site location, subsurface exploration, description of subsurface conditions, recommended foundation options, and then steering design parameters, estimate settlement of foundations, recommend the nations for design of county construction and interior floor slab.”

Committee members also discussed optional services included in the proposal. An optional package priced in the contract — identified in the meeting as roughly $16,000 — was not selected; the project lead said it was included to capture a price should additional borings be needed later but that the likelihood of needing more borings beyond the contract scope was “not very likely.”

A committee member asked whether any borings had been performed before the county purchased the property. Speaker 3 answered: “No.”

Formal action: a motion to approve and authorize the contract passed after a voice vote. The motion text recorded in the meeting packet was to approve and authorize a contract with InterTech, DSI, to provide soil-boring services for the LEC site. The transcript records a motion “by God” and a second “by Latic.” The voice vote was recorded as “Aye,” with one dissenting voice: “Opposed, Terry.” The committee’s packet identifies the work as a required preliminary step to inform foundation design and stormwater/retention planning for the site.

The committee’s approval allows staff to execute the contract and begin the geotechnical investigation on the schedule stated in the contract summary form.