City awards $13.18 million contract for Lower Gulpha gravity sewer phases 2—6

5405347 · July 16, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The city awarded a $13,183,721 contract to Belt Construction Inc. for phases 2—4 of the Lower Gulpha Lower Gravity Sewer Capacity Improvement Project; the work is funded by 2025 wastewater bonds and is connected to ADEQ consent order LIS22-077.

The City of Hot Springs on July 15 adopted Resolution R-25-143, awarding a $13,183,721 contract to Belt Construction Inc. to build phases 2, 3 and 4 (Schedule 2) of the Lower Gulpha Lower Gravity Sewer Capacity Improvement Project, city staff told the board.

"The award shall be in the total lump sum price of $13,183,721, which is approximately $2,500,000 under staff budget estimates," Joyce Stadler, assistant engineering project manager, told the board. Stadler said the work includes approximately 9,300 feet of 36-inch pipe and 4,600 feet of 30-inch fiberglass reinforced pipe and starts north of the Phase 1 alignment behind Lakeside School.

Stadler also said the project is included in a Department of Environmental Quality consent administrative order, CAO LIS22-077, and is funded by board-approved 2025 wastewater bonds.

Two bids were received; Belt Construction Inc. was the lowest responsive bidder, Stadler said. A notice of intent was posted and no bid protests were received. The board adopted the resolution by roll call; all voting members recorded affirmative votes.

City staff said the contract award is roughly $2.5 million below staff estimates and that work follows design by RGN Group. No public comment was recorded on the item at the July 15 meeting.